Red Hill Construction and Civil, established in 2016, boasts an outstanding track record of excellence. We specialise in Form, Reinforcement and Pour (FRP) needs and have successfully completed major civil infrastructure projects all over Australia.
Our experienced management team has the expertise to manage all stages of constructing roads, bridge works, and rail infrastructure.
We take pride in offering first-class workmanship from inception and planning of works to completion and finishing. No matter what phase your project is in, we deliver exceptional results.
Central Station Metro
Scope of Work
Site Setup, Concrete FRP, Combined Services Routes (CSR), Hoarding installation, Temporary Works
Location
Central Station
Completion Date
2019 – 2023
Client
Laing O’Rourke
Redfern Station Upgrade
Scope of Work
Location
Completion Date
August 2022
Client
Novo Rail for the Transport for NSW Redfern Station Upgrade project
St Marys Metro Enabling Works
Scope of Work
Location
Completion Date
December 2022
Client
Shellharbour Station - MTMS
Scope of Work
Location
Completion Date
December 2022
Client
Transport For Tomorrow
Redfern Station Platform Resurfacing
Scope of Work
Demolition of existing asphalt platform, earthworks, asphalting station platforms, Works within rail corridor.
Location
Redfern Station
Completion Date
2023
Client
Novo Rail for the Transport for NSW Redfern Station Upgrade project
Wards Parramatta
Scope of Work
Installation of 2250m2 concrete crane pad, installation of bentonite treatment slab,
Location
Parramatta
Completion Date
April 2023
Client
Laing O’Rourke
Perth Metronet Melconnx
Scope of Work
TBA
Location
Perth
Completion Date
Current
Client
Waterfall Station
Scope of Work
Piling installation, excavation, sheet pile shoring, waterproofing and pile cap FRP construction
Location
St. Mary’s Metro Enabling Works
Completion Date
December 2022
Client
Transport For Tomorrow
Cranbrook WA
Scope of Work
TBA
Location
Perth
Completion Date
Current
Client
Wollongong Stabling
Scope of Work
Installation and finishing xxxxm of concrete foot path
Location
Waterfall Station
Completion Date
May 2023
Client
Transport for Tomorrow